The MHC heaters are set to the Eclipse setting every May, usually around the 5th. They are reset to the Post Eclipse setting every September, usually on the 30th. The master database with the updated heaters settings needs to be made available to the planners at ISAS at least a week before it is uploaded in the plan.
There are 2 studies which control the MHC heaters settings; default_htrs1_6 and default_htrs7_12 .
Details for the studies are summarised in the following table:Database Id | default_htrs1_6 | default_htrs7_12 |
---|---|---|
Master Database Id | 000143 | 000144 |
PM Database Id | 000101 | 000102 |
These 2 studies are used for both the Eclipse and Post Eclipse settings.
The procedure to update the MHC heaters is split into two parts; the first updates study default_htrs1_6 and the second updates study default_htrs7_12.The eclipse heater studies can be viewed here.
The post-eclipse heater studies can be viewed here.
The cycling of the heaters for both settings can be seen here.
The heaters schedule can be seen here.
This procedure is used to update both the eclipse and post_eclipse settings. The appropriate choices are highlighted in various steps of the procedure.
That's it, all finished!